Charter are a turnkey security shutter provider, working from the initial design concept to the manufacturing and onsite requirements.

  Process Action By  Time
1 From receipt of order, working drawings processed outlining scope of works and interface with surrounding trades Charter 1 week
2 Working drawings approved by contractor Client TBC
3 Cavity closer shutter side guide manufactured and delivered to site Charter 3 weeks from
drawing approval
4 Roller shutter lintels manufactured and delivered to site Charter 4 weeks from
drawing approval
5 Cavity closer side guide and roller shutter lintel installed in line with method statement Client Varies
6 Charter Project manager monitors site progress and arranges for a site survey once cavity closer side guides and roller shutter lintels are installed Charter 1 day
7 Roller shutters are manufactured to surveyed dimensions Charter 4 weeks from
survey date
8 Fully employed Charter engineers attend site and install the roller shutters Charter Varies, typically
5-10 per day
9 Site manager checks the installations and signs off project as complete Client  
10 Electrical work including control wiring and electrical connections carried out by others Client  
  • Dedicated project
    manager per project;
    ensures communication
    is clear and frequent
  • Fully qualified engineer
    teams; all CSCS accredited
    and familiar with
    construction site
    procedure
  • Complete manufacturing
    capacity; ability to work
    to required timescales
  • Detailed working
    drawings with every
    project; clarity with scope
    of works and surrounding trades